NexusRMS uses a standard 5×5 risk matrix to quantify hazards consistently across all RAMS documents and standalone risk assessments. This methodology aligns with HSE guidance and provides a clear, auditable framework for risk evaluation and control prioritisation.
5×5 Risk Matrix
The risk matrix plots Likelihood against Severity to produce a numerical risk score:
| Score | Likelihood | Severity |
|---|---|---|
| 1 | Rare | Negligible |
| 2 | Unlikely | Minor |
| 3 | Possible | Moderate |
| 4 | Likely | Major |
| 5 | Almost Certain | Catastrophic |
The Risk Score is calculated as Likelihood × Severity, producing a value in the range of 1 to 25.
Risk Levels
| Level | Score Range | Colour | Action Required |
|---|---|---|---|
| Low | 1–6 | Green | Manage by routine procedures |
| Medium | 7–12 | Yellow | Specific risk reduction measures required |
| High | 13–19 | Orange | Senior management attention; significant controls required |
| Critical | 20–25 | Red | Immediate action required; work must not proceed until risk is reduced |
Initial vs Residual Risk
Each hazard is assessed twice:
- Initial Risk — the risk score before any control measures are applied; represents the inherent danger of the hazard
- Residual Risk — the risk score after control measures have been implemented; represents the managed risk level
The Risk Reduction metric is calculated as the initial score minus the residual score. This value measures the effectiveness of your control measures. A higher risk reduction indicates more effective mitigation.
Per-Hazard Risk Assessment
Within the RAMS Document Builder, each hazard includes interactive risk assessment controls:
- Likelihood Slider — adjust from 1 (Rare) to 5 (Almost Certain)
- Severity Slider — adjust from 1 (Negligible) to 5 (Catastrophic)
- Real-Time Score — the risk score and level update instantly as sliders are adjusted
Live Risk Summary
The Live Risk Summary component provides a real-time visualisation of the risk matrix across all hazards in the current document. As hazards are added, removed, or reassessed, the summary updates to show the distribution of risks across the matrix.
Standalone Risk Assessments
The system supports standalone formal risk assessments via the RiskAssessment model for assessments outside a specific RAMS document. Standalone assessments include:
- Assessment Name — descriptive title for the assessment
- Location — site or area being assessed
- Date — date the assessment was carried out
- Assessed By / Reviewed By — persons responsible for conducting and reviewing the assessment
- Next Review Date — scheduled date for reassessment
Assessor Qualification Tracking
The system tracks assessor qualifications to ensure competency:
- SMSTS — Site Management Safety Training Scheme
- SSSTS — Site Supervisor Safety Training Scheme
- H&S Qualification — general health and safety certification (e.g. NEBOSH, IOSH)
Control Effectiveness Rating
Each control measure can be rated for effectiveness after implementation:
- Not Assessed — effectiveness has not yet been evaluated
- Ineffective — control does not adequately reduce the risk
- Partially Effective — control provides some risk reduction but gaps remain
- Effective — control adequately reduces the risk to an acceptable level
- Highly Effective — control significantly exceeds the minimum requirement
Database Computed Columns
Risk scores are stored as PostgreSQL computed columns using the storedAs directive. The columns risk_score_before, risk_score_after, and risk_reduction are automatically calculated by the database engine, ensuring consistency and enabling efficient queries and aggregations without application-level computation.